5. System validation tests
Based on the experience of a pre-series base run in 2000-2002, it was decided to divide the validation of the ERTMS system into four phases:
a platform and simulator phase (figure 13 );
a phase with a test train, but on a site limited in length and speed (figure 14 );
a phase with the test train on a 40 km site at a maximum speed of 160 km/h, with the possibility of simulating trains running ahead of the test train;
a phase on the actual LGV site.
The test platform with its equipment, edges, floors and environmental simulators was included...
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
![](/assets/images/logo-eti-286623ed91fa802ce039246e516e5852.png)
The Ultimate Scientific and Technical Reference
This article is included in
Railway systems
This offer includes:
Knowledge Base
Updated and enriched with articles validated by our scientific committees
Services
A set of exclusive tools to complement the resources
Practical Path
Operational and didactic, to guarantee the acquisition of transversal skills
Doc & Quiz
Interactive articles with quizzes, for constructive reading
System validation tests
References
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
![](/assets/images/logo-eti-286623ed91fa802ce039246e516e5852.png)
The Ultimate Scientific and Technical Reference