
5. System validation tests
Based on the experience of a pre-series base run in 2000-2002, it was decided to divide the validation of the ERTMS system into four phases:
a platform and simulator phase (figure 13 );
a phase with a test train, but on a site limited in length and speed (figure 14 );
a phase with the test train on a 40 km site at a maximum speed of 160 km/h, with the possibility of simulating trains running ahead of the test train;
a phase on the actual LGV site.
The test platform with its equipment, edges, floors and environmental simulators was included...
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!

The Ultimate Scientific and Technical Reference
This article is included in
Electricity networks and applications
This offer includes:
Knowledge Base
Updated and enriched with articles validated by our scientific committees
Services
A set of exclusive tools to complement the resources
Practical Path
Operational and didactic, to guarantee the acquisition of transversal skills
Doc & Quiz
Interactive articles with quizzes, for constructive reading
System validation tests
References
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!

The Ultimate Scientific and Technical Reference