2. Project implementation, actions taken
2.1 Project chronology
In terms of its initial objectives, the project was rolled out in the following main phases:
April to July 2009: Diagnosis with analysis of existing situation, consideration of needs and definition of recommendations, with implementation schedule;
September 2009 to September 2010: detailed definition and implementation of recommendations ;
October 2010 to May 2011: training of project managers and project referents in collaborative project management, completion of four pilot projects and implementation of the chosen software platform;
June 2011 to April 2012: assessment of the work carried out and general deployment...
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
![](/assets/images/logo-eti-286623ed91fa802ce039246e516e5852.png)
The Ultimate Scientific and Technical Reference
This article is included in
Management and innovation engineering
This offer includes:
Knowledge Base
Updated and enriched with articles validated by our scientific committees
Services
A set of exclusive tools to complement the resources
Practical Path
Operational and didactic, to guarantee the acquisition of transversal skills
Doc & Quiz
Interactive articles with quizzes, for constructive reading
Project implementation, actions taken
Bibliography
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
![](/assets/images/logo-eti-286623ed91fa802ce039246e516e5852.png)
The Ultimate Scientific and Technical Reference