6. Installation. Installation
To achieve greater reliability and shorter on-site assembly times, the modular indoor substation is highly industrialized. All HV equipment is assembled, adjusted and tested at the factory, then transported to the site, where only the sub-assemblies are assembled.
The construction of the modular indoor substation, for the HV part, includes the following phases:
construction of the substation's reception slab and grounding network;
construction of the steel-frame building that forms the load-bearing structure;
assembly of prefabricated subassemblies in this building;
control wiring for non prefabricated elements ;
verifications.
In a modular indoor...
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
![](/assets/images/logo-eti-286623ed91fa802ce039246e516e5852.png)
The Ultimate Scientific and Technical Reference
This article is included in
Electricity networks and applications
This offer includes:
Knowledge Base
Updated and enriched with articles validated by our scientific committees
Services
A set of exclusive tools to complement the resources
Practical Path
Operational and didactic, to guarantee the acquisition of transversal skills
Doc & Quiz
Interactive articles with quizzes, for constructive reading
Installation. Installation
References
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
![](/assets/images/logo-eti-286623ed91fa802ce039246e516e5852.png)
The Ultimate Scientific and Technical Reference